DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.1.5A rate analysis

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) )

Published rate₹6,347.75per cum
Rate analysis

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :

DSR rate₹6,347.75per cum

1:3:6 (1 Cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA) )

Item code
4.1.5A
Sub-head
SH 4 · CONCRETE WORK
Unit
cum
Source row
4

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
0279 Recycled Concrete Aggregate (RCA) 20 mm nominal size cum 0.7 ₹957.00 ₹669.90
0281 Recycled Concrete Aggregate (RCA) 10 mm nominal size cum 0.24 ₹957.00 ₹229.68
2202 Carriage of Recycled Concrete Aggregate (RCA) below 40 mm nominal size cum 0.94 ₹0.00 ₹0.00
0278 Manufactured sand derived from Recycled Concrete Aggregate (RCA) cum 0.47 ₹957.00 ₹449.79
2203 Carriage of manufactured sand cum 0.47 ₹0.00 ₹0.00
0367 Portland Cement (0.15674 cum) tonne 0.22 ₹5,156.00 ₹1,134.32
2209 Carriage of Cement tonne 0.22 ₹0.00 ₹0.00
LABOUR
0155 Mason (average) day 0.1 ₹857.00 ₹85.70
0114 day 1.63 ₹736.00 ₹1,199.68
0101 Bhisti day 0.7 ₹816.00 ₹571.20
0002 Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper day 0.07 ₹900.00 ₹63.00
0012 Vibrator(Needle type 40mm) day 0.07 ₹400.00 ₹28.00
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹4,461.96
Add 1 % Water charges on "W" ₹44.62
TOTAL ₹4,506.58
Add GST on "X" (multiplying factor 0.2127) ₹958.55
TOTAL ₹5,465.13
Add 15% CPOH on "Y" ₹819.77
TOTAL ₹6,284.90
Add Cess @ 1% on "Z" ₹62.85
Cost of 1 cum. ₹6,347.75
Say ₹6,347.75

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook