Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.
Uni Axial Woven polyster geogrid of minimum tensile strength 250KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction.
Published rate₹819.65per sqm
Rate analysis
Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.
DSR rate₹819.65per sqm
Uni Axial Woven polyster geogrid of minimum tensile strength 250KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction.
Item code
26.84.8
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4335
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of Cost for 300 Sqm.
MATERIALS:
8986
Uni Axial Woven polyster geogrid of minimum tensile strength 250KN/m in the Longitudinal direction and 30KN/m in the Transverse direction.
sqm
300
₹526.00
₹1,57,800.00
—
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item in all respect including transportation. i.e 5% of (P)
—
—
—
₹7,890.00
LABOUR:
0128
Mate
day
0.36
₹816.00
₹293.76
0114
Beldar
day
6
₹736.00
₹4,416.00
0139
Skilled Beldar
day
3
₹816.00
₹2,448.00
Rate build-up
Total
₹1,72,847.76
Add 1 % Water charges on "W"
₹1,728.48
TOTAL
₹1,74,576.24
Add GST on "X" (multiplying factor 0.2127)
₹37,132.37
TOTAL
₹2,11,708.61
Add 15% CPOH on "Y"
₹31,756.29
TOTAL
₹2,43,464.90
Add Cess @ 1% on "Z"
₹2,434.65
Cost of 300 sqm
₹2,45,899.55
Cost of 1 sqm
₹819.67
Say
₹819.65
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.