Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge. Uni Axial Woven polyster geogrid of minimum tensile strength 120KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction.

Published rate₹470.10per sqm
Rate analysis

Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-in- charge.

DSR rate₹470.10per sqm

Uni Axial Woven polyster geogrid of minimum tensile strength 120KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction.

Item code
26.84.5
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
4335

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of Cost for 300 Sqm.
MATERIALS:
8983 Uni Axial Woven polyster geogrid of minimum tensile strength 120KN/m in the Longitudinal direction and 30KN/m in the Transverse direction. sqm 300 ₹292.00 ₹87,600.00
Add 5 percent of the cost of reinforcing elements geogrid for wastage and accessories like tie-strips, nuts and bolts and loops/lungs for joining reinforcing elements with the facia panels, overlaps and other protective elements for geogrid and all other activities required to complete the item  in all respect including transportation.i.e 5% of (P) ₹4,380.00
LABOUR:
0128 Mate day 0.36 ₹816.00 ₹293.76
0114 Beldar day 6 ₹736.00 ₹4,416.00
0139 Skilled Beldar day 3 ₹816.00 ₹2,448.00

Rate build-up

Total ₹99,137.76
Add 1 % Water charges on "W" ₹991.38
TOTAL ₹1,00,129.14
Add GST on "X" (multiplying factor 0.2127) ₹21,297.47
TOTAL ₹1,21,426.61
Add 15% CPOH on "Y" ₹18,213.99
TOTAL ₹1,39,640.60
Add Cess @ 1% on "Z" ₹1,396.41
Cost of 300 sqm ₹1,41,037.01
Cost of 1 sqm ₹470.12
Say ₹470.10