DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.74.3 rate analysis

Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately) Extra for using M-50 (Cement content 425 kg) instead of M-35

Published rate₹450.40DSR 2023
Rate analysis

Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately)

DSR rate₹450.40as per item analysis

Extra for using M-50 (Cement content 425 kg) instead of M-35

Item code
26.74.3
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
See analysis
Source row
3870

Cost components

CodeDescriptionUnitQuantityRateAmount
Cement for M-35 Mix = 0.370 T
Cement for M-50 Mix = 0.425 T
Difference 0.055 T
0367 Portland Cement tonne 0.055 ₹5,156.00 ₹283.58
2209 Carriage of cement tonne 0.055 ₹0.00 ₹0.00
Plasticizer for M-35 Mix =7.400 Kgs
Plasticizer for M-50 Mix = 8.500 Kgs
Difference 1.100Kgs
7318 Plasticizer or Super Plasticizer 2% of cement content kg 1.1 ₹30.00 ₹33.00

Rate build-up

TOTAL ₹316.58
Add 1 % Water charges on "W" ₹3.17
TOTAL ₹319.75
Add GST on "X" (multiplying factor 0.2127) ₹68.01
TOTAL ₹387.76
Add 15% CPOH on "Y" ₹58.16
TOTAL ₹445.92
Add Cess @ 1% on "Z" ₹4.46
Cost of 1.00 Cum ₹450.38
Say ₹450.40

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook