Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately) Concrete grade M-35 (Cement content 370 kgs)

Published rate₹20,928.70DSR 2023
Rate analysis

Fabrication and manufacturing of solid precast concrete element with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix as per the direction of Engineer-in-Charge (Cost of reinforcement, Mechanical, Electrical and Plumbing inserts will be paid separately). Note: Excess/less cement over the specified cement content used as per design mix is payable/recoverable separately)

DSR rate₹20,928.70as per item analysis

Concrete grade M-35 (Cement content 370 kgs)

Item code
26.74.1
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
See analysis
Source row
3870

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 1.26 Cum
Considers a wall 2.80 X 3.00 X 0.15 = 1.260 Cum
5.33.2.3 Rate as per Item No.5.33.2.3 of SH: RCC M25 cum 1.26 ₹10,162.35 ₹12,804.56
5.35 Rate as per item no 5.35 of SH RCC quintal 0.252 ₹733.50 ₹184.84
9999 Cost of hosting and fixing moulds L.S. 372 ₹2.27 ₹844.44
Side Shuttering of walls ((2.8+3)x2x0.15=1.74)
5.9.1 Rate as per item No.5.9.1 of SH : RCC sqm 1.74 ₹392.15 ₹682.34
9999 Table buffing & oiling L.S. 174 ₹2.27 ₹394.98
9999 Sundries (Extra labour for Lifting, transportation, stacking of finished precast elements) L.S. 230 ₹2.27 ₹522.10
5.41.1 Rate as per item no 5.41.1 of SH RCC (Curing using curing compound) sqm 18.54 ₹69.05 ₹1,280.19
7929 Shear loops (6mm dia GI wire rope) (For vertical joints) 6 nos on each side each 12 ₹230.00 ₹2,760.00
7930 dowel tubes (Corrugated GI pipes 50 to 80mm dia) (For horizontal joints m 3 ₹165.00 ₹495.00
9999 Shear key (6mm thick mechanically folded MS plate) L.S. 115 ₹2.27 ₹261.05
7931 Hooks for lifting (Alloy steel) having 2.5 tonne capacity each 2 ₹310.00 ₹620.00
Labour for fixing accessories & inserts such as shear loops, shear keys, dowel tubes, lifting hooks
0155 Mason (average) day 0.5 ₹857.00 ₹428.50
0115 Coolie day 0.5 ₹736.00 ₹368.00
Labour for operating of hoisting & fixing moulds
0157 Operator day 0.5 ₹897.00 ₹448.50
0116 Fitter (grade 1) day 0.3 ₹897.00 ₹269.10
0115 Coolie day 0.3 ₹736.00 ₹220.80
9999 Sundries (Labour cost such as crane, trailer(flat bed & a frames) & panel racks for stacking of precost concrete panel wall) L.S. 173.41 ₹2.27 ₹393.64

Rate build-up

TOTAL ₹22,978.04
Add 1 % Water charges on "W-A" ₹80.26
TOTAL ₹23,058.30
Add GST on "X-A" (multiplying factor 0.2127) ₹1,724.22
TOTAL ₹24,782.52
Add 15% CPOH on "Y-A" ₹1,474.59
TOTAL ₹26,257.11
Add Cess @ 1% on "Z-A" ₹113.05
Cost of 1.26cum ₹26,370.16
Cost for 1 cum ₹20,928.70
Say ₹20,928.70