DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.65 rate analysis

Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet confirming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately).

Published rate₹1,525.60per sqm
Rate analysis

Providing and fixing roofing consist of 0.8 mm thick galvanized steel deck sheet confirming to IS 277:1992 used as permanent shuttering over which MS wire mesh 3mm laid at 100x100 mm grid including edge trim covered with concrete. This metal deck will be supported on structural steel beam with shear studs. (Structural steel like Beam, column, joists etc. & concrete of different grade as per design will be paid separately).

DSR rate₹1,525.60per sqm
Item code
26.65
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
3067

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
Weight of GI sheet for 10sqm = 76.7 kgs + Add wastage @ 3% = 2.3 kg. Total = 79.00 kg
8019 GI sheet 0.8 mm thick confirming to IS 277:1992 kg 79 ₹69.00 ₹5,451.00
Length wire mesh 200metre/10 sqm. Weight of wire @ 0.06 kg/m. total weight = 12 kgs + Add wastage @ 5% = 0.6 kgs. Total 12.6 kg
1217 GI Wire mesh 100x100 mm kg 12.6 ₹75.00 ₹945.00
2314 Carriage of sheet & wire tonne 0.092 ₹0.00 ₹0.00
1218 Shear stud each 40 ₹50.00 ₹2,000.00
9999 Nails/Tagged screws L.S. 138.7 ₹2.27 ₹314.85
9999 Labour for fixing shear stud L.S. 462.4 ₹2.27 ₹1,049.65
Labour for sheeting (Ref item no 26.19.1)
0130 Mistry day 0.108 ₹897.00 ₹96.88
0112 Carpenter 2nd class day 0.432 ₹816.00 ₹352.51
0114 Beldar day 0.432 ₹736.00 ₹317.95
Labour for laying wire mesh (Ref item no 5.22.2)
0102 Blacksmith 1st class day 0.12 ₹897.00 ₹107.64
0114 Beldar day 0.12 ₹736.00 ₹88.32

Rate build-up

Total ₹10,723.80
Add 1 % Water charges on "W" ₹107.24
TOTAL ₹10,831.04
Add GST on "X" (multiplying factor 0.2127) ₹2,303.76
TOTAL ₹13,134.80
Add 15% CPOH on "Y" ₹1,970.22
TOTAL ₹15,105.02
Add Cess @ 1% on "Z" ₹151.05
Cost of 10 sqm ₹15,256.07
Cost of 1 sqm ₹1,525.61
Say ₹1,525.60

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook