Rate analysis
Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels.
DSR rate₹49.30per metre
- Item code
- 26.58
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- metre
- Source row
- 2888
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 48 metre | |||||
| MATERIAL | |||||
| 8520 | Elastobar / equivalent | kg | 1 | ₹300.00 | ₹300.00 |
| 0367 | OPC Cement | tonne | 0.002 | ₹5,156.00 | ₹10.31 |
| 9999 | 100 mesh silica, water, technical supervision, etc. | L.S. | 3 | ₹2.27 | ₹6.81 |
| LABOUR | |||||
| 0123 | Mason (Brick layer) 1st class | day | 1.5 | ₹897.00 | ₹1,345.50 |
Rate build-up
| TOTAL | ₹1,662.62 |
| Add 1% water charges | ₹16.63 |
| TOTAL | ₹1,679.25 |
| Add GST on "X" (multiplying factor 0.2127) | ₹357.18 |
| TOTAL | ₹2,036.43 |
| Add 15% CPOH on "Y" | ₹305.46 |
| TOTAL | ₹2,341.89 |
| Add Cess @1% on "Z" | ₹23.42 |
| Cost of 48 metre | ₹2,365.31 |
| Cost of 1 metre | ₹49.28 |
| Say | ₹49.30 |