DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.58 rate analysis

Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels.

Published rate₹49.30per metre
Rate analysis

Filling of joints between RCC plinth beam / floor slab and wall panel of external walls, toilet / bath room / wet areas walls on all floor and parapet wall over roof slab, stair case head room at the time of erection of GFRG panels with Grout RW/equivalent sealant compound after the erection of panel before the infill of concrete in panel cavities and fine finish. This applies for all horizontal and vertical joints between GFRG wall and slab panels.

DSR rate₹49.30per metre
Item code
26.58
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
metre
Source row
2888

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 48 metre
MATERIAL
8520 Elastobar / equivalent kg 1 ₹300.00 ₹300.00
0367 OPC Cement tonne 0.002 ₹5,156.00 ₹10.31
9999 100 mesh silica, water, technical supervision, etc. L.S. 3 ₹2.27 ₹6.81
LABOUR
0123 Mason (Brick layer) 1st class day 1.5 ₹897.00 ₹1,345.50

Rate build-up

TOTAL ₹1,662.62
Add 1% water charges ₹16.63
TOTAL ₹1,679.25
Add GST on "X" (multiplying factor 0.2127) ₹357.18
TOTAL ₹2,036.43
Add 15% CPOH on "Y" ₹305.46
TOTAL ₹2,341.89
Add Cess @1% on "Z" ₹23.42
Cost of 48 metre ₹2,365.31
Cost of 1 metre ₹49.28
Say ₹49.30

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook