CPWD DSR item 26.46 rate analysis

Providing and fixing in position, 200 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree) . The EPS core shall consist of 100 mm thick EPS of density not less than 20 kg/ per cum. Both the outer faces of the panel shall be finished by applying the layer of 50 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100Kn/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge.

Published rate₹4,347.15per sqm
Rate analysis

Providing and fixing in position, 200 mm thick factory made Expanded Polystyrene Core (EPS Core) wall panels consisting of EPS core sandwiched between two Engineered sheets of welded wire fabric mesh duly finished with shortcrete materials on outer faces. The fabric mesh shall be made of 3 mm dia G.I. wire mesh with 50 mm pitch in both the directions and on both faces of the wall, kept at 120-135 mm gap and connected by the zig zag G.I. wire of 3 mm dia at alternate row by welding (at an angle ranging from 50-70 degree) . The EPS core shall consist of 100 mm thick EPS of density not less than 20 kg/ per cum. Both the outer faces of the panel shall be finished by applying the layer of 50 mm thick cement mortar 1:3 {1 cement: 3 coarse sand (not having more than 40% stone chips of size upto 6 mm)} À with the help of shotcreting/guniting equipment etc at a pressure not less than 1 bar (100Kn/m2) and both surfaces finished with trowel. Fixing operations of wall panels shall be completed in all respect as per drawings and specifications and under the overall direction of the Engineer-in-charge.

DSR rate₹4,347.15per sqm
Item code
26.46
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
sqm
Source row
2324

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.20x3.00m= 3.60 sqm
MATERIAL
8013 Factory made EPS Core wallpanel /roof panel sandwiched between two Engineered welded wire fabric mesh of 3 mm dia G.I. wire mesh,with 50 mm pitch in both the directions, kept at 120-135 mm gap and interconnected by the zig zag G.I. wire of 3 mm dia at alternate row by welding. sqm 3.78 ₹1,708.00 ₹6,456.24
3.60 sqm + 0.18 sqm (Add for wastage @5%)Total = 3.78 sqm
9999 Add for L-shape,U-shape & straight lap mesh L.S. 208 ₹2.27 ₹472.16
Cement mortar 1:3 (1cement:3 coarse sand)
2x1.20x3.00x0.05= 0.36 cum
3.8 Rate as per Item No.3.8 of SH: Mortar cum 0.36 ₹4,881.95 ₹1,757.50
10 mm TMT bars (2 nos.75 mm long)
Aluminium C-channels (100mmx150mm long)
9999 For fixing wall with foundation L.S. 312.15 ₹2.27 ₹708.58
LABOUR
9999 For carrying out shotcreting, shoring, leveling, and finishing the surface with trowel. L.S. 707.5 ₹2.27 ₹1,606.03

Rate build-up

TOTAL ₹11,000.51
Add 1 % Water charges on "W" ₹110.01
TOTAL ₹11,110.52
Add GST on "X" (multiplying factor 0.2127) ₹2,363.21
TOTAL ₹13,473.73
Add 15% CPOH on "Y" ₹2,021.06
TOTAL ₹15,494.79
Add Cess @ 1% on "Z" ₹154.95
Cost of 3.60 sqm ₹15,649.74
Cost of 1 sqm ₹4,347.15
Say ₹4,347.15