Rate analysis
Providing, erecting, maintaining and removing temporary protective screens made out of specified fabric with all necessary fixing arrangement to ensure that it remains in position for the work duration as required by the Engineer-in-charge.
DSR rate₹54.25as per item analysis
Wooven PVC cloth
- Item code
- 26.36.1
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- See analysis
- Source row
- 1875
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 sqm | |||||
| MATERIAL | |||||
| 7915 | Wooven PVC cloth | sqm | 10 | ₹28.00 | ₹280.00 |
| 9999 | Fixing double scaffolding outside | L.S. | 11 | ₹2.27 | ₹24.97 |
| — | Total Material | — | — | — | ₹304.97 |
| LABOUR | |||||
| — | For fixing and removal after complete of work @25% | — | — | — | ₹76.24 |
| — | Rate for 10 sqm | — | — | — | ₹542.32 |
| — | Rate for 1 sqm | — | — | — | ₹54.23 |
Rate build-up
| TOTAL | ₹381.21 |
| Add 1 % Water charges on "W" | ₹3.81 |
| TOTAL | ₹385.02 |
| Add GST on "X" (multiplying factor 0.2127) | ₹81.89 |
| TOTAL | ₹466.91 |
| Add 15% CPOH on "Y" | ₹70.04 |
| TOTAL | ₹536.95 |
| Add Cess @ 1% on "Z" | ₹5.37 |
| Say | ₹54.25 |