Rate analysis
Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of approved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and allowing it to dry, all complete as per direction of Engineer-In-Charge.
DSR rate₹8.25as per item analysis
Bars upto 12 mm diameter
- Item code
- 26.29.1
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- See analysis
- Source row
- 1497
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 3.00 sqm (95.54 meter length of 10 mm dia bar) Bars upto 12 mm diameter | |||||
| (1 litre chemical shall cover 3.00 sqm area of bars) | |||||
| MATERIALS | |||||
| 7911 | Chemical Rust Remover | litre | 1 | ₹290.00 | ₹290.00 |
| LABOUR | |||||
| (Application charges for 3.0 sqm) | |||||
| 0131 | Painter | day | 0.162 | ₹816.00 | ₹132.19 |
| 0115 | Coolie | day | 0.162 | ₹736.00 | ₹119.23 |
| 9999 | Putty, brush, sand paper | L.S. | 3.162 | ₹2.27 | ₹7.18 |
| 9999 | Sundries | L.S. | 1.98 | ₹2.27 | ₹4.49 |
| — | Rate per meter length of bar | — | — | — | ₹8.24 |
Rate build-up
| TOTAL | ₹553.09 |
| Add 1 % Water charges on "W" | ₹5.53 |
| TOTAL | ₹558.62 |
| Add GST on "X" (multiplying factor 0.2127) | ₹118.82 |
| TOTAL | ₹677.44 |
| Add 15% CPOH on "Y" | ₹101.62 |
| TOTAL | ₹779.06 |
| Add Cess @ 1% on "Z" | ₹7.79 |
| Cost of 3 sqm (95.54 m length of 10 mm dia bar) | ₹786.85 |
| Say | ₹8.25 |