DSR 2023 · SH 26 · NEW TECHNOLOGIES AND

CPWD DSR item 26.28.2 rate analysis

Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge 50mm average thickness

Published rate₹256.35DSR 2023
Rate analysis

Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge

DSR rate₹256.35as per item analysis

50mm average thickness

Item code
26.28.2
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
See analysis
Source row
1436

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for One Sqm
50mm average thickness for beams
MACHINERY
9999 Hire charges for HILTY-TE 504 Pneumatic Chisel L.S. 3.74 ₹2.27 ₹8.49
LABOUR
0157 Machine Operator day 0.134 ₹897.00 ₹120.20
0114 Beldar day 0.07 ₹736.00 ₹51.52

Rate build-up

TOTAL ₹180.21
Add 1 % Water charges on "W" ₹1.80
TOTAL ₹182.01
Add GST on "X" (multiplying factor 0.2127) ₹38.71
TOTAL ₹220.72
Add 15% CPOH on "Y" ₹33.11
TOTAL ₹253.83
Add Cess @ 1% on "Z" ₹2.54
Cost of 1.0 sqm ₹256.37
Say ₹256.35