Supplying & laying of drainage composite for use behind walls, between two different fills, alongside drains of road, below concrete lining of canals etc. having thermobonding a draining core - HDPE geonet comprises of two sets of parallel overlayed ribs integrally connected to have a rhomboidal shape with a polyethylene film and a nonwoven geotextile having mass per unit area 130 gsm and tensile strength of 8.0 kN/m that will be working as separation or protecting layer, geocomposite having in plane flow capacity of 0.7 L / (m.s) at hydraulic gradient of 1.0 & 20 kPa pressure and tensile strength of 13.5 kN/m , with mass per unit area of 830 gsm, at easily accessible location including top and bottom, with all leads and lifts, manpower and machinery, materials, labour etc. complete and as directed by Engineer - In - Charge.
Published rate₹1,166.95per Sqm
Rate analysis
Supplying & laying of drainage composite for use behind walls, between two different fills, alongside drains of road, below concrete lining of canals etc. having thermobonding a draining core - HDPE geonet comprises of two sets of parallel overlayed ribs integrally connected to have a rhomboidal shape with a polyethylene film and a nonwoven geotextile having mass per unit area 130 gsm and tensile strength of 8.0 kN/m that will be working as separation or protecting layer, geocomposite having in plane flow capacity of 0.7 L / (m.s) at hydraulic gradient of 1.0 & 20 kPa pressure and tensile strength of 13.5 kN/m , with mass per unit area of 830 gsm, at easily accessible location including top and bottom, with all leads and lifts, manpower and machinery, materials, labour etc. complete and as directed by Engineer - In - Charge.
DSR rate₹1,166.95per Sqm
Item code
26.17
Sub-head
SH 26 · NEW TECHNOLOGIES AND
Unit
Sqm
Source row
670
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Material
Details of Cost for 300 Sqm
8961
Geosynthetic Drainage Composite
sqm
300
₹724.00
₹2,17,200.00
—
Add 10 per cent of the cost of synthetic Composits for wastage and accessories for joining sheets with the facia pannels, overlaps and other protective elements for synthetic Composits and other miscelleneus activities required to complete the item in all respect including transpotarion & takes. 10% of "P"
—
—
—
₹21,720.00
0128
Mate
day
0.36
₹816.00
₹293.76
0114
Beldar
day
6
₹736.00
₹4,416.00
0139
Skilled Beldar
day
3
₹816.00
₹2,448.00
Rate build-up
TOTAL
₹2,46,077.76
Add 1 % Water charges on "W"
₹2,460.78
TOTAL
₹2,48,538.54
Add GST on "X" (multiplying factor 0.2127)
₹52,864.15
TOTAL
₹3,01,402.69
Add 15% CPOH on "Y"
₹45,210.40
TOTAL
₹3,46,613.09
Add Cess @ 1% on "Z"
₹3,466.13
Cost for 300 Sqm
₹3,50,079.22
Cost per Sqm
₹1,166.93
Say
₹1,166.95