Rate analysis
Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 40kN/m in the longitudinal and transverse direction, with 14kN/m and 28kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening.
DSR rate₹555.05per Sqm
- Item code
- 26.15
- Sub-head
- SH 26 · NEW TECHNOLOGIES AND
- Unit
- Sqm
- Source row
- 627
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of Cost for 300 Sqm | |||||
| MATERIAL | |||||
| 8959 | Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 40kN/m in the longitudinal and transverse direction | Sqm | 300 | ₹333.00 | ₹99,900.00 |
| — | Add 10 per cent of the cost of reinforcing elements (synthetic geogrids) for wastage and accessories like tie-strips, nuts and bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geogrids and all other activities required to complete the item in all respect including taxes and transportation. 10% of "P" | — | — | — | ₹9,990.00 |
| LABOUR | |||||
| 0128 | Mate | day | 0.36 | ₹816.00 | ₹293.76 |
| 0114 | Beldar | day | 6 | ₹736.00 | ₹4,416.00 |
| 0139 | Skilled Beldar | day | 3 | ₹816.00 | ₹2,448.00 |
Rate build-up
| TOTAL | ₹1,17,047.76 |
| Add 1 % Water charges on "W" | ₹1,170.48 |
| TOTAL | ₹1,18,218.24 |
| Add GST on "X" (multiplying factor 0.2127) | ₹25,145.02 |
| TOTAL | ₹1,43,363.26 |
| Add 15% CPOH on "Y" | ₹21,504.49 |
| TOTAL | ₹1,64,867.75 |
| Add Cess @ 1% on "Z" | ₹1,648.68 |
| Cost for 300 Sqm | ₹1,66,516.43 |
| Cost per Sqm | ₹555.05 |
| Say | ₹555.05 |