Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level. Rocky strata including Boulders 300 mm dia

Published rate₹1,870.60per metre
Rate analysis

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level. Rocky strata including Boulders

DSR rate₹1,870.60per metre

300 mm dia

Item code
23.2.2.1
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
metre
Source row
188

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 16 metre
MACHINERY :
0020 Hydraulic Excavator (3D) with driver and fuel. day 0.9 ₹7,850.00 ₹7,065.00
1235 Diesel oil litre 10 ₹89.62 ₹896.20
Extra diesel required for boring in rockystrata
0005 Hire charges of Diesel Truck - 9 tonne day 0.429 ₹4,400.00 ₹1,887.60
Transportation charges for to and fro to site (assume 140m of bore for one shifting) (2 x30)/140Loading, unloading &Errection charges of drilling Rig Machine
LABOUR
0114 Beldar day 4 ₹736.00 ₹2,944.00
0130 Mistry day 1 ₹897.00 ₹897.00
7763 Water supply tanker of 5000 litre capacity each 1 ₹1,625.00 ₹1,625.00
Extra labour to assist M/C operator &security
0134 Rock Hole Driller day 1 ₹736.00 ₹736.00
0114 Beldar day 5 ₹736.00 ₹3,680.00
0103 Blacksmith 2nd class day 0.7 ₹816.00 ₹571.20
0113 Chowkidar day 1 ₹736.00 ₹736.00

Rate build-up

TOTAL ₹21,038.00
Add 1 % Water charges on "W" ₹210.38
TOTAL ₹21,248.38
Add GST on "X" (multiplying factor 0.2127) ₹4,519.53
TOTAL ₹25,767.91
Add 15% CPOH on "Y" ₹3,865.19
TOTAL ₹29,633.10
Add Cess @ 1% on "Z" ₹296.33
Cost for 16 metre ₹29,929.43
Cost of 1 metre ₹1,870.59
Say ₹1,870.60