Rate analysis
Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer -in-charge, beyond 90 metre & upto 150 metre depth below ground level. All types of soil
DSR rate₹917.40per metre
350 mm dia
- Item code
- 23.2.1.2
- Sub-head
- SH 23 · RAIN WATER HARVESTING &
- Unit
- metre
- Source row
- 188
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 27 metre | |||||
| MACHINERY : | |||||
| 0020 | Hydraulic Excavator (3D) with driver and fuel. | day | 1 | ₹7,850.00 | ₹7,850.00 |
| 0005 | Hire charges of Diesel Truck - 9 tonne | day | 0.429 | ₹4,400.00 | ₹1,887.60 |
| Transportation charges for to and fro to site | |||||
| (assume 140m of bore for one shifting) (2 x30)/140 | |||||
| Loading, unloading &Errection charges of drilling Rig Machine | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 4 | ₹736.00 | ₹2,944.00 |
| 0130 | Mistry | day | 1 | ₹897.00 | ₹897.00 |
| 7763 | Water supply tanker of 5000 litre capacity | each | 1 | ₹1,625.00 | ₹1,625.00 |
| Extra labour to assist M/C operator &security | |||||
| 0114 | Beldar | day | 2 | ₹736.00 | ₹1,472.00 |
| 0113 | Chowkidar | day | 1 | ₹736.00 | ₹736.00 |
Rate build-up
| TOTAL | ₹17,411.60 |
| Add 1 % Water charges on "W" | ₹174.12 |
| TOTAL | ₹17,585.72 |
| Add GST on "X" (multiplying factor 0.2127) | ₹3,740.48 |
| TOTAL | ₹21,326.20 |
| Add 15% CPOH on "Y" | ₹3,198.93 |
| TOTAL | ₹24,525.13 |
| Add Cess @ 1% on "Z" | ₹245.25 |
| Cost for 27 metre | ₹24,770.38 |
| Cost of 1 metre | ₹917.42 |
| Say | ₹917.40 |