Rate analysis
200 mm nominal size dia having minimum wall thickness 5.40 mm
DSR rate₹2,442.75per metre
- Item code
- 23.10.3
- Sub-head
- SH 23 · RAIN WATER HARVESTING &
- Unit
- metre
- Source row
- 663
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 30 metre | |||||
| MATERIAL | |||||
| 7744 | M.S. pipe 200 mm dia casing pipe | metre | 30 | ₹1,550.00 | ₹46,500.00 |
| 7766 | M.S. socket 200 mm dia | each | 5 | ₹300.00 | ₹1,500.00 |
| 2345 | Carriage of cast iron pipes 200 mm dia | 100 metre | 0.3 | ₹0.00 | ₹0.00 |
| including loading and unloading Painting with anticorrosive Paint 3.14 x0.210x30.00=20.25 sqm. | |||||
| 13.65.1 | Rate as per Item No.13.65.1 of SH:Finishing | sqm | 20.25 | ₹140.25 | ₹2,840.06 |
| LABOUR | |||||
| 0114 | Beldar | day | 1.45 | ₹736.00 | ₹1,067.20 |
| 0130 | Mistry | day | 0.5 | ₹897.00 | ₹448.50 |
Rate build-up
| TOTAL | ₹52,355.76 |
| Add 1 % Water charges on "W-A" | ₹495.16 |
| TOTAL | ₹52,850.92 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹10,637.31 |
| TOTAL | ₹63,488.23 |
| Add 15% CPOH on "Y-A" | ₹9,097.23 |
| TOTAL | ₹72,585.46 |
| Add Cess @ 1% on "Z-A" | ₹697.45 |
| Cost for 30 metre | ₹73,282.91 |
| Cost of 1 metre | ₹2,442.76 |
| Say | ₹2,442.75 |