DSR 2023 · SH 23 · RAIN WATER HARVESTING &

CPWD DSR item 23.10.3 rate analysis

200 mm nominal size dia having minimum wall thickness 5.40 mm

Published rate₹2,442.75per metre
Rate analysis

200 mm nominal size dia having minimum wall thickness 5.40 mm

DSR rate₹2,442.75per metre
Item code
23.10.3
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
metre
Source row
663

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 30 metre
MATERIAL
7744 M.S. pipe 200 mm dia casing pipe metre 30 ₹1,550.00 ₹46,500.00
7766 M.S. socket 200 mm dia each 5 ₹300.00 ₹1,500.00
2345 Carriage of cast iron pipes 200 mm dia 100 metre 0.3 ₹0.00 ₹0.00
including loading and unloading Painting with anticorrosive Paint 3.14 x0.210x30.00=20.25 sqm.
13.65.1 Rate as per Item No.13.65.1 of SH:Finishing sqm 20.25 ₹140.25 ₹2,840.06
LABOUR
0114 Beldar day 1.45 ₹736.00 ₹1,067.20
0130 Mistry day 0.5 ₹897.00 ₹448.50

Rate build-up

TOTAL ₹52,355.76
Add 1 % Water charges on "W-A" ₹495.16
TOTAL ₹52,850.92
Add GST on "X-A" (multiplying factor 0.2127) ₹10,637.31
TOTAL ₹63,488.23
Add 15% CPOH on "Y-A" ₹9,097.23
TOTAL ₹72,585.46
Add Cess @ 1% on "Z-A" ₹697.45
Cost for 30 metre ₹73,282.91
Cost of 1 metre ₹2,442.76
Say ₹2,442.75

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook