CPWD DSR item 23.1.2.3 rate analysis

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level. Rocky strata including Boulders 400 mm dia

Published rate₹2,131.45per metre
Rate analysis

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level. Rocky strata including Boulders

DSR rate₹2,131.45per metre

400 mm dia

Item code
23.1.2.3
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
metre
Source row
5

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 16 metre
MACHINERY :
0020 Hydraulic Excavator (3D) with driver and fuel. day 0.9 ₹7,850.00 ₹7,065.00
1235 Diesel oil litre 16 ₹89.62 ₹1,433.92
Extra diesel required for boring in rockystrata
0005 Hire charges of Diesel Truck - 9 tonne day 0.429 ₹4,400.00 ₹1,887.60
Transportation charges for to and fro to site
(assume 140m of bore for one shifting) (2x30)/140
Loading, unloading &Errection charges of drilling Rig Machine
LABOUR
0114 Beldar day 4 ₹736.00 ₹2,944.00
0130 Mistry day 1 ₹897.00 ₹897.00
7763 Water supply tanker of 5000 litre capacity each 1 ₹1,625.00 ₹1,625.00
Extra labour to assist M/C operator &security
0134 Rock Hole Driller day 1.2 ₹736.00 ₹883.20
0114 Beldar day 8 ₹736.00 ₹5,888.00
0103 Blacksmith 2nd class day 0.75 ₹816.00 ₹612.00
0113 Chowkidar day 1 ₹736.00 ₹736.00

Rate build-up

TOTAL ₹23,971.72
Add 1 % Water charges on "W" ₹239.72
TOTAL ₹24,211.44
Add GST on "X" (multiplying factor 0.2127) ₹5,149.77
TOTAL ₹29,361.21
Add 15% CPOH on "Y" ₹4,404.18
TOTAL ₹33,765.39
Add Cess @ 1% on "Z" ₹337.65
Cost for 16 metre ₹34,103.04
Cost of 1 metre ₹2,131.44
Say ₹2,131.45