DSR 2023 · SH 23 · RAIN WATER HARVESTING &

CPWD DSR item 23.1.2.1 rate analysis

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level. Rocky strata including Boulders 300 mm dia

Published rate₹1,695.10per metre
Rate analysis

Boring/drilling bore well of required dia for casing/ strainer pipe, by suitable method prescribed in IS: 2800 (part I), including collecting samples from different strata, preparing and submitting strata chart/ bore log, including hire & running charges of all equipments, tools, plants & machineries required for the job, all complete as per direction of Engineer-in-charge, upto 90 metre depth below ground level. Rocky strata including Boulders

DSR rate₹1,695.10per metre

300 mm dia

Item code
23.1.2.1
Sub-head
SH 23 · RAIN WATER HARVESTING &
Unit
metre
Source row
5

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 16 metre
MACHINERY :
0020 Hydraulic Excavator (3D) with driver and fuel. day 0.9 ₹7,850.00 ₹7,065.00
1235 Diesel oil litre 6 ₹89.62 ₹537.72
Extra diesel required for boring in rocky strata
0005 Hire charges of Diesel Truck - 9 tonne day 0.429 ₹4,400.00 ₹1,887.60
Transportation charges for to and fro to site
(assume 140m of bore for one shifting) (2 x30)/140
Loading, unloading &Errection charges of drilling Rig Machine
LABOUR
0114 Beldar day 4 ₹736.00 ₹2,944.00
0130 Mistry day 1 ₹897.00 ₹897.00
7763 Water supply tanker of 5000 litre capacity each 1 ₹1,625.00 ₹1,625.00
Extra labour to assist M/C operator & security
0134 Rock Hole Driller day 0.75 ₹736.00 ₹552.00
0114 Beldar day 3 ₹736.00 ₹2,208.00
0103 Blacksmith 2nd class day 0.75 ₹816.00 ₹612.00
0113 Chowkidar day 1 ₹736.00 ₹736.00

Rate build-up

TOTAL ₹19,064.32
Add 1 % Water charges on "W" ₹190.64
TOTAL ₹19,254.96
Add GST on "X" (multiplying factor 0.2127) ₹4,095.53
TOTAL ₹23,350.49
Add 15% CPOH on "Y" ₹3,502.57
TOTAL ₹26,853.06
Add Cess @ 1% on "Z" ₹268.53
Cost for 16 metre ₹27,121.59
Cost of 1 metre ₹1,695.10
Say ₹1,695.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook