DSR 2023 · SH 21 · ALUMINIUM WORK

CPWD DSR item 21.3.3 rate analysis

Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item): With float glass panes of 8 mm thickness (weight not less than 20 kg/sqm)

Published rate₹1,685.40DSR 2023
Rate analysis

Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item):

DSR rate₹1,685.40as per item analysis

With float glass panes of 8 mm thickness (weight not less than 20 kg/sqm)

Item code
21.3.3
Sub-head
SH 21 · ALUMINIUM WORK
Unit
See analysis
Source row
380

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.00 sqm
MATERIAL
Float Glass panes 8.0 mm thick = 1.00 sqm
Add for wastage & breakage @ 10% = 0.10 sqm
Total =1.10 sqm
2408 Float glass sheet of nominal thickness 8 mm.(weight not less than 20.00 kg/sqm). sqm 1.1 ₹641.00 ₹705.10
9977 Carriage of glass L.S. 4.84 ₹2.27 ₹10.99
7390 Neoprene/EPDM rubber gasket metre 6 ₹16.00 ₹96.00
LABOUR
0112 Carpenter 2nd class day 0.23 ₹816.00 ₹187.68
0114 Beldar day 0.23 ₹736.00 ₹169.28
9988 Sundries and carriage of gasket L.S. 6.89 ₹2.27 ₹15.64

Rate build-up

TOTAL ₹1,184.69
Add 1 % Water charges on "W" ₹11.85
TOTAL ₹1,196.54
Add GST on "X" (multiplying factor 0.2127) ₹254.50
TOTAL ₹1,451.04
Add 15% CPOH on "Y" ₹217.66
TOTAL ₹1,668.70
Add Cess @ 1% on "Z" ₹16.69
Cost for 1 sqm ₹1,685.39
Say ₹1,685.40