DSR 2023 · SH 21 · ALUMINIUM WORK

CPWD DSR item 21.3.1 rate analysis

Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item): With float glass panes of 4.0 mm thickness (weight not less than 10kg/sqm)

Published rate₹1,176.80DSR 2023
Rate analysis

Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item):

DSR rate₹1,176.80as per item analysis

With float glass panes of 4.0 mm thickness (weight not less than 10kg/sqm)

Item code
21.3.1
Sub-head
SH 21 · ALUMINIUM WORK
Unit
See analysis
Source row
380

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.00 sqm
MATERIAL
Float Glass panes 4.0 mm thick = 1.00 sqm
Add for wastage & breakage @ 10% = 0.10 sqm
Total =1.10 sqm
2406 Float glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm). sqm 1.1 ₹321.00 ₹353.10
9977 Carriage of glass L.S. 2.42 ₹2.27 ₹5.49
7390 Neoprene/EPDM rubber gasket metre 6 ₹16.00 ₹96.00
LABOUR
0112 Carpenter 2nd class day 0.23 ₹816.00 ₹187.68
0114 Beldar day 0.23 ₹736.00 ₹169.28
9988 Sundries and carriage of gasket L.S. 6.89 ₹2.27 ₹15.64

Rate build-up

TOTAL ₹827.19
Add 1 % Water charges on "W" ₹8.27
TOTAL ₹835.46
Add GST on "X" (multiplying factor 0.2127) ₹177.70
TOTAL ₹1,013.16
Add 15% CPOH on "Y" ₹151.97
TOTAL ₹1,165.13
Add Cess @ 1% on "Z" ₹11.65
Cost for 1 sqm ₹1,176.78
Say ₹1,176.80