Rate analysis
Providing and fixing double glazed hermetically sealed glazing in aluminium windows, ventilators and partition etc. with 6 mm thick clear float glass both side, having 12 mm air gap, including providing EPDM gasket, perforated aluminium spacers, desiccants, sealant (Both primary and secondary sealant) etc. as per specifications, drawings and direction of Engineer-in-charge complete.
DSR rate₹4,997.70as per item analysis
- Item code
- 21.1
- Sub-head
- SH 21 · ALUMINIUM WORK
- Unit
- See analysis
- Source row
- 715
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1.00 sqm | |||||
| MATERIAL | |||||
| Hermetically sealled double glazed unit made with 6mm thick clear float glass both side having 12 mm air gap = 1.00 sqm. | |||||
| Add for wastage & breakage @ 10% = 0.10 sqm | |||||
| Total = 1.10 sqm | |||||
| 8648 | Hermetically sealed double glazed unit made with 6 mm thick clear float glass both side having 12 mm air gap | sqm | 1.1 | ₹2,600.00 | ₹2,860.00 |
| 9977 | Carriage of glass | L.S. | 6.66 | ₹2.27 | ₹15.12 |
| 7390 | Neoprene/EPDM rubber gasket | metre | 6 | ₹16.00 | ₹96.00 |
| LABOUR | |||||
| Glazier / | |||||
| 0112 | Carpenter 2nd class | day | 0.23 | ₹816.00 | ₹187.68 |
| 0114 | Beldar | day | 0.46 | ₹736.00 | ₹338.56 |
| 9988 | Sundries and carriage of gasket | L.S. | 6.89 | ₹2.27 | ₹15.64 |
Rate build-up
| TOTAL | ₹3,513.00 |
| Add 1 % Water charges on "W" | ₹35.13 |
| TOTAL | ₹3,548.13 |
| Add GST on "X" (multiplying factor 0.2127) | ₹754.69 |
| TOTAL | ₹4,302.82 |
| Add 15% CPOH on "Y" | ₹645.42 |
| TOTAL | ₹4,948.24 |
| Add Cess @ 1% on "Z" | ₹49.48 |
| Cost for 1 sqm | ₹4,997.72 |
| Say | ₹4,997.70 |