Providing, driving (with vibrating pile driving hammer complete with power units & accessories) and installing driven Pre-cast reinforced cement concrete piles of specified diameter and length below the pile cap in M-25 cement concrete to carry safe working load not less than specified with a central through preformed hole with M.S. black pipe of dia, 40 mm for grouting with cement sand grouting of mix 1:2 (1cement : 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap).
500 mm dia piles
Published rate₹4,931.35DSR 2023
Rate analysis
Providing, driving (with vibrating pile driving hammer complete with power units & accessories) and installing driven Pre-cast reinforced cement concrete piles of specified diameter and length below the pile cap in M-25 cement concrete to carry safe working load not less than specified with a central through preformed hole with M.S. black pipe of dia, 40 mm for grouting with cement sand grouting of mix 1:2 (1cement : 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap).
DSR rate₹4,931.35as per item analysis
500 mm dia piles
Item code
20.5.3
Sub-head
SH 20 · PILE WORK
Unit
See analysis
Source row
713
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 20 m length of pile
MATERIAL
Concrete -3.14/4x(0.50)²x20 = 3.925 cum
5.33.1.1
Rate as per item no 5.33.1.1 of SH : RCC Work
cum
3.925
₹9,504.75
₹37,306.14
5.19
Add Rate as per item no 5.19 of SH : RCC
cum
3.925
₹16,089.40
₹63,150.90
5.1.3
Deduct Rate as per item no 5.1.3 SH : RCC
cum
-3.925
₹8,583.40
-₹33,689.85
Cement mortar 1:2 for grout
3.7
Rate as per Item Number 3.7 of SH: Mortars
cum
0.025
₹5,584.50
₹139.61
9999
Sundries
L.S.
442
₹2.27
₹1,003.34
7181
C.I. pile shoe of 80 kg per pile
kilogram
80
₹52.00
₹4,160.00
7182
M.S. clamps for pile shoe of 35 kg per pile
kilogram
35
₹45.00
₹1,575.00
MACHINERY
0027
Hire and running charges of vibrating pile driving hammer complete with power unit and accessories
day
0.38
₹33,500.00
₹12,730.00
0028
Hire and running charges of crane 20 tonne capacity.
day
0.06
₹7,850.00
₹471.00
LABOUR
Work supervisor
0130
Mistry
day
0.12
₹897.00
₹107.64
0114
Beldar
day
3
₹736.00
₹2,208.00
—
Add 15% CP & OH on "Y-A"
—
—
—
₹4,114.43
Rate build-up
Total
₹89,161.78
Add 1% water charges on "W -A"
₹223.95
TOTAL
₹89,385.73
Add GST on "X-A" (multiplying factor 0.2127)
₹4,810.96
TOTAL
₹94,196.69
TOTAL
₹98,311.12
Add 1% cess on "Z -A"
₹315.44
Cost of 20 m pile
₹98,626.56
Cost for 1 m pile
₹4,931.33
Say
₹4,931.35
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.