DSR 2023 · SH 20 · PILE WORK

CPWD DSR item 20.4.4 rate analysis

Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter(only the nos. of extra bulbs are to be paid) 550 mm dia piles

Published rate₹3,360.15per bulb
Rate analysis

Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter(only the nos. of extra bulbs are to be paid)

DSR rate₹3,360.15per bulb

550 mm dia piles

Item code
20.4.4
Sub-head
SH 20 · PILE WORK
Unit
bulb
Source row
608

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 bulb.
MATERIAL
Bulb - 0.102 cum
5.33.1.1 Rate as per item no 5.33.1.1 of SH : RCC Work cum 0.102 ₹9,504.75 ₹969.48
7183 Bentonite tonne 0.01 ₹3,050.00 ₹30.50
MACHINERY
0024 Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site. day 0.02 ₹39,500.00 ₹790.00
0025 Hire and running charges of light crane. day 0.01 ₹3,900.00 ₹39.00
0026 Hire and running charges of bentonite pump. day 0.02 ₹3,350.00 ₹67.00
LABOUR
Work supervisor
0130 Mistry day 0.02 ₹897.00 ₹17.94
0114 Beldar day 1 ₹736.00 ₹736.00
Add 15% CP & OH on "Y-A" ₹308.74

Rate build-up

Total ₹2,649.92
Add 1% water charges on "W -A" ₹16.80
TOTAL ₹2,666.72
Add GST on "X-A" (multiplying factor 0.2127) ₹361.00
TOTAL ₹3,027.72
TOTAL ₹3,336.46
Add 1% cess on "Z -A" ₹23.67
Cost of 1 bulb ₹3,360.13
Say ₹3,360.15