DSR 2023 · SH 20 · PILE WORK

CPWD DSR item 20.3.3 rate analysis

Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap) : 450 mm dia piles

Published rate₹4,232.75DSR 2023
Rate analysis

Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap) :

DSR rate₹4,232.75as per item analysis

450 mm dia piles

Item code
20.3.3
Sub-head
SH 20 · PILE WORK
Unit
See analysis
Source row
495

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metres
MATERIAL
RCC-Stem -3.14/4x(0.45)²x9.212 = 1.465 cum, Bulb -3.14/4x(1.125)²x0.113 = 0.112 cum, 2x 3.14/4x(0.788)²x0.337 = 0.329 cum, Total = 1.906 cum
5.33.1.1 Rate as per item no 5.33.1.1 of SH : RCC Work cum 1.906 ₹9,504.75 ₹18,116.05
7183 Bentonite tonne 0.19 ₹3,050.00 ₹579.50
9999 Sundries L.S. 165 ₹2.27 ₹374.55
MACHINERY
0024 Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site. day 0.36 ₹39,500.00 ₹14,220.00
0025 Hire and running charges of light crane. day 0.06 ₹3,900.00 ₹234.00
0026 Hire and running charges of bentonite pump. day 0.02 ₹3,350.00 ₹67.00
LABOUR
Work supervisor
0130 Mistry day 0.08 ₹897.00 ₹71.76
0114 Beldar day 2 ₹736.00 ₹1,472.00
Add 15% CP & OH on "Y-A" ₹3,126.77

Rate build-up

Total ₹35,134.86
Add 1% water charges on "W -A" ₹170.19
TOTAL ₹35,305.05
Add GST on "X-A" (multiplying factor 0.2127) ₹3,656.10
TOTAL ₹38,961.15
TOTAL ₹42,087.92
Add 1% cess on "Z -A" ₹239.72
Cost of 10 m pile ₹42,327.64
Cost for 1 m pile ₹4,232.76
Say ₹4,232.75