Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used.
600 mm dia piles
Published rate₹5,386.25DSR 2023
Rate analysis
Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted, telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tube well boring machine shall not be used.
DSR rate₹5,386.25as per item analysis
600 mm dia piles
Item code
20.2A.1
Sub-head
SH 20 · PILE WORK
Unit
See analysis
Source row
343
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 20 m length of pile
MATERIAL
Concrete 3.14/4x0.60²x20 = 5.65 cum
5.33.1.1
Rate as per item no 5.33.1.1 of SH : RCC Work
cum
5.65
₹9,504.75
₹53,701.84
7183
Bentonite
tonne
0.33
₹3,050.00
₹1,006.50
9999
Sundries
L.S.
110
₹2.27
₹249.70
MACHINERY
0024
Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site.
day
0.75
₹39,500.00
₹29,625.00
0025
Hire and running charges of light crane.
day
0.06
₹3,900.00
₹234.00
0026
Hire and running charges of bentonite pump.
day
0.38
₹3,350.00
₹1,273.00
0018
Hire and running charges of loader
day
0.3
₹6,700.00
₹2,010.00
0017
Hire and running charges of tipper
day
0.3
₹4,200.00
₹1,260.00
LABOUR
Work supervisor
0130
Mistry
day
0.12
₹897.00
₹107.64
0114
Beldar
day
3
₹736.00
₹2,208.00
—
Add 15% CP & OH on "Y-A"
—
—
—
₹6,976.71
Rate build-up
Total
₹91,675.68
Add 1% water charges on "W -A"
₹379.74
TOTAL
₹92,055.42
Add GST on "X-A" (multiplying factor 0.2127)
₹8,157.81
TOTAL
₹1,00,213.23
TOTAL
₹1,07,189.94
Add 1% cess on "Z -A"
₹534.88
Cost of 20 m pile
₹1,07,724.82
Cost for 1 m pile
₹5,386.24
Say
₹5,386.25
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.