DSR 2023 · SH 20 · PILE WORK

CPWD DSR item 20.2.3 rate analysis

Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by percussion drilling using Direct mud circulation (DMC) or Bailer and chisel technique by tripod and mechanical Winch Machine all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tubewell boring machine shall not be used . 600 mm dia piles

Published rate₹3,637.20DSR 2023
Rate analysis

Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by percussion drilling using Direct mud circulation (DMC) or Bailer and chisel technique by tripod and mechanical Winch Machine all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be measured up to bottom of pile cap). Note: Truck Mounted rotary/TMR/Tubewell boring machine shall not be used .

DSR rate₹3,637.20as per item analysis

600 mm dia piles

Item code
20.2.3
Sub-head
SH 20 · PILE WORK
Unit
See analysis
Source row
221

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 20 m length of pile
MATERIAL
Concrete 3.14/4x0.60²x20 = 5.65 cum
5.33.1.1 Rate as per item no 5.33.1.1 of SH : RCC Work cum 5.65 ₹9,504.75 ₹53,701.84
7183 Bentonite tonne 0.33 ₹3,050.00 ₹1,006.50
9999 Sundries L.S. 115 ₹2.27 ₹261.05
MACHINERY
0015 Hire and running charges of Tripod and Mechanical Winch machine complete with power unit and accessories day 1.5 ₹3,350.00 ₹5,025.00
0025 Hire and running charges of light crane. day 0.06 ₹3,900.00 ₹234.00
0026 Hire and running charges of bentonite pump. day 0.38 ₹3,350.00 ₹1,273.00
0018 Hire and running charges of loader day 0.3 ₹6,700.00 ₹2,010.00
0017 Hire and running charges of tipper day 0.3 ₹4,200.00 ₹1,260.00
LABOUR
Work supervisor
0130 Mistry day 0.12 ₹897.00 ₹107.64
0114 Beldar day 3 ₹736.00 ₹2,208.00
Add 15% CP & OH on "Y-A" ₹2,459.18

Rate build-up

Total ₹67,087.03
Add 1% water charges on "W -A" ₹133.85
TOTAL ₹67,220.88
Add GST on "X-A" (multiplying factor 0.2127) ₹2,875.50
TOTAL ₹70,096.38
TOTAL ₹72,555.56
Add 1% cess on "Z -A" ₹188.54
Cost of 20 m pile ₹72,744.10
Cost for 1 m pile ₹3,637.21
Say ₹3,637.20

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook