DSR 2023 · SH 20 · PILE WORK

CPWD DSR item 20.1.4 rate analysis

Providing, driving with hydraulic piling rigs with power units and installing driven cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap) : 550 mm dia piles

Published rate₹4,530.90DSR 2023
Rate analysis

Providing, driving with hydraulic piling rigs with power units and installing driven cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap) :

DSR rate₹4,530.90as per item analysis

550 mm dia piles

Item code
20.1.4
Sub-head
SH 20 · PILE WORK
Unit
See analysis
Source row
4

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 20 m length of pile
Concrete 3.14/4x0.55²x20 = 4.75 cum
5.33.1.1 Rate as per item no 5.33.1.1 of SH : RCC Work cum 4.75 ₹9,504.75 ₹45,147.56
9999 Sundries L.S. 330 ₹2.27 ₹749.10
7181 C.I. pile shoe of 80 kg per pile @ 80 kg per pile kilogram 80 ₹52.00 ₹4,160.00
7182 M.S. clamps for pile shoe of 35 kg per pile kilogram 35 ₹45.00 ₹1,575.00
MACHINERY
0024 Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site. day 0.6 ₹39,500.00 ₹23,700.00
0025 Hire and running charges of light crane. day 0.06 ₹3,900.00 ₹234.00
LABOUR
Work supervisor
0130 Mistry day 0.08 ₹897.00 ₹71.76
0114 Beldar day 2 ₹736.00 ₹1,472.00
Add 15% CP & OH on "Y-A" ₹5,872.16

Rate build-up

Total ₹77,109.42
Add 1% water charges on "W -A" ₹319.62
TOTAL ₹77,429.04
Add GST on "X-A" (multiplying factor 0.2127) ₹6,866.27
TOTAL ₹84,295.31
TOTAL ₹90,167.47
Add 1% cess on "Z -A" ₹450.20
Cost of 20 m pile ₹90,617.67
Cost for 1 m pile ₹4,530.88
Say ₹4,530.90