Rate analysis
Providing, driving with hydraulic piling rigs with power units and installing driven cast-in-situ reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap) :
DSR rate₹3,430.65as per item analysis
450 mm dia piles
- Item code
- 20.1.2
- Sub-head
- SH 20 · PILE WORK
- Unit
- See analysis
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 20 m length of pile | |||||
| Concrete -3.14/4x0.45²x20 = 3.18 cum | |||||
| 5.33.1.1 | Rate as per item no 5.33.1.1 of SH : RCC Work | cum | 3.18 | ₹9,504.75 | ₹30,225.11 |
| 9999 | Sundries | L.S. | 225 | ₹2.27 | ₹510.75 |
| 7181 | C.I. pile shoe of 80 kg per pile @ 80 kg per pile | kilogram | 80 | ₹52.00 | ₹4,160.00 |
| 7182 | M.S. clamps for pile shoe of 35 kg per pile | kilogram | 35 | ₹45.00 | ₹1,575.00 |
| MACHINERY | |||||
| 0024 | Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at site. | day | 0.48 | ₹39,500.00 | ₹18,960.00 |
| 0025 | Hire and running charges of light crane. | day | 0.06 | ₹3,900.00 | ₹234.00 |
| LABOUR | |||||
| Work supervisor | |||||
| 0130 | Mistry | day | 0.08 | ₹897.00 | ₹71.76 |
| 0114 | Beldar | day | 2 | ₹736.00 | ₹1,472.00 |
| — | Add 15% CP & OH on "Y-A" | — | — | — | ₹4,957.52 |
Rate build-up
| Total | ₹57,208.62 |
| Add 1% water charges on "W -A" | ₹269.84 |
| TOTAL | ₹57,478.46 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹5,796.79 |
| TOTAL | ₹63,275.25 |
| TOTAL | ₹68,232.77 |
| Add 1% cess on "Z -A" | ₹380.08 |
| Cost of 20 m pile | ₹68,612.85 |
| Cost for 1 m pile | ₹3,430.64 |
| Say | ₹3,430.65 |