Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) with R.C.C. top slab with 1:1.5:3 mix (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1 cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement complete as per standard design : Inside size 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm internal diameter, total weight of cover and frame to be not less than 116 kg (weight of cover 58 kg and weight of frame 58 kg) :
With Sewer bricks conforming to IS : 4885
Published rate₹26,244.70DSR 2023
Rate analysis
Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) with R.C.C. top slab with 1:1.5:3 mix (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1 cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement complete as per standard design : Inside size 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty) 500 mm internal diameter, total weight of cover and frame to be not less than 116 kg (weight of cover 58 kg and weight of frame 58 kg) :
DSR rate₹26,244.70as per item analysis
With Sewer bricks conforming to IS : 4885
Item code
19.7.2.2
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
1167
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 1 manhole
MATERIAL
Cement concrete 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)
1.81x1.51x0.20 m = 0.547 cum Say 0.55 cum
4.1.8
Rate as per item no 4.1.8 of SH : Concrete Work
cum
0.55
₹6,812.00
₹3,746.60
Brick work with modular extruded brunt fly ash clay sewer bricks (Conforming to IS: 4885 ) in cement mortar 1:4 (1 cement : 4 coarse sand)
5.12x0.23x0.80 m = 0.942 cum
Less for pipe 2x3.14x(0.15m)²x0.23m = (-) 0.008 cum
= 0.934 cum Say 0.93 cum
6.36.1
Rate as per item No 6.36.1 of SH : Brick Work
cum
0.93
₹7,197.75
₹6,693.91
Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) for benching
2x1.20x(0.90/2) x (0.30+0.20)/2 = 2.70 cum
Less for pipe 1.20x3.14/4x(0.15m)² = (-) 0.021 cum
= 0.249 cum say 0.25
4.1.3
Rate as per item no. 4.1.3 of SH : Concrete Work
cum
0.25
₹7,878.50
₹1,969.63
12 mm cement plaster 1:3 (1 cement : 3 coarse sand) finished with floating coat of neat cement
4.20mx0.50m = 2.10 sqm
2x½x0.90x0.10m = 0.09sqm
= 2.19 sqm
13.9.1
Rate as per item no 13.9.1 of SH : Finishing
sqm
2.19
₹449.55
₹984.51
Reinforced cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
For slab : 1.66x1.36x0.15m = 0.339 cum
Less for cover 0.7854x(0.50)²x0.15m = (-) 0.029 cum
= 0.31 cum
5.1.2
Rate as per item no. 5.1.2 of SH : RCC work
cum
0.31
₹9,045.75
₹2,804.18
T.M.T. bars steel reinforcement for R.C.C work of slab
0.31 cum @ 80.09 kg/cum = 24.83 kg
5.22.6
Rate as per item no. 5.22.6 of SH : RCC work
kg
24.83
₹107.85
₹2,677.92
Form work = 1.20x0.90 = 1.08 sqm
Less cover = 3.14/4x(0.50)² = (-) 0.196 sqm
= 0.884 sqm Say 0.88 sqm
5.9.3
Rate as per item no 5.9.3 of SH : RCC Work
sqm
0.88
₹927.25
₹815.98
LABOUR
Extra labour for making channel :
0123
Mason 1st class
day
0.08
₹897.00
₹71.76
0124
Mason 2nd class
day
0.08
₹816.00
₹65.28
1356
500 mm dia cover with frame (medium duty)
each
1
₹4,400.00
₹4,400.00
9977
Carriage of C.I. cover & frame
L.S.
6.76
₹2.27
₹15.35
9999
Painting of C.I. cover & frame with coal tar
L.S.
6.76
₹2.27
₹15.35
9999
Sundries
L.S.
16.64
₹2.27
₹37.77
Rate build-up
TOTAL
₹24,298.24
Add 1 % Water charges on "W-A"
₹46.06
TOTAL
₹24,344.30
Add GST on "X-A" (multiplying factor 0.2127)
₹989.39
TOTAL
₹25,333.69
Add 15% CPOH on "Y-A"
₹846.14
TOTAL
₹26,179.83
Add Cess @ 1% on "Z-A"
₹64.87
Cost of each
₹26,244.70
Say
₹26,244.70
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.