Rate analysis
Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete :
DSR rate₹4,750.85per metre
900 mm dia. R.C.C. pipe
- Item code
- 19.6.10
- Sub-head
- SH 19 · DRAINAGE
- Unit
- metre
- Source row
- 752
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 metre | |||||
| MATERIAL | |||||
| 1710 | R.C.C. pipes NP2 class 900 mm dia | metre | 10 | ₹2,728.00 | ₹27,280.00 |
| (in 2.5 m. length = 4 Nos.) | |||||
| 1724 | R.C.C. collars NP2 class 900 mm dia | each | 4 | ₹260.00 | ₹1,040.00 |
| 4 Nos. | |||||
| 2331 | Carriage of R.C.C. pipes 900 mm dia | 100 metre | 0.1 | ₹0.00 | ₹0.00 |
| Cement of 4 joints = 4x0.0082 = 0.0328 cum = 0.0488 t Say 0.049 | |||||
| 0367 | Portland Cement (OPC-43 grade) | tonne | 0.049 | ₹5,156.00 | ₹252.64 |
| 2209 | Carriage of Cement | tonne | 0.049 | ₹0.00 | ₹0.00 |
| Fine sand for 4 joints = 0.0164x4 = 0.066 cum | |||||
| 0983 | Fine sand (zone IV) | cum | 0.066 | ₹980.00 | ₹64.68 |
| 2261 | Carriage of Fine sand (1 part badarpur sand : 2 parts jamuna sand) | cum | 0.066 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 1.25 | ₹897.00 | ₹1,121.25 |
| 0124 | Mason 2nd class | day | 1.25 | ₹816.00 | ₹1,020.00 |
| 0114 | Beldar | day | 3 | ₹736.00 | ₹2,208.00 |
| 0101 | Bhisti | day | 0.5 | ₹816.00 | ₹408.00 |
Rate build-up
| TOTAL | ₹33,394.57 |
| Add 1 % Water charges on "W" | ₹333.95 |
| TOTAL | ₹33,728.52 |
| Add GST on "X" (multiplying factor 0.2127) | ₹7,174.06 |
| TOTAL | ₹40,902.58 |
| Add 15% CPOH on "Y" | ₹6,135.39 |
| TOTAL | ₹47,037.97 |
| Add Cess @ 1% on "Z" | ₹470.38 |
| Cost of 10 metres | ₹47,508.35 |
| Cost of 1 metre | ₹4,750.84 |
| Say | ₹4,750.85 |