DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.5.4 rate analysis

Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps : 250 mm diameter

Published rate₹111.00per metre
Rate analysis

Dismantling of old S.W. pipes including breaking of joints and bed concrete stacking of useful materials near the site within 50 m lead and disposal of unserviceable materials into municipal dumps :

DSR rate₹111.00per metre

250 mm diameter

Item code
19.5.4
Sub-head
SH 19 · DRAINAGE
Unit
metre
Source row
606

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metre
LABOUR
0114 Beldar day 0.49 ₹736.00 ₹360.64
0115 Coolie day 0.57 ₹736.00 ₹419.52

Rate build-up

TOTAL ₹780.16
Add 1 % Water charges on "W" ₹7.80
TOTAL ₹787.96
Add GST on "X" (multiplying factor 0.2127) ₹167.60
TOTAL ₹955.56
Add 15% CPOH on "Y" ₹143.33
TOTAL ₹1,098.89
Add Cess @ 1% on "Z" ₹10.99
Cost of 10 metres ₹1,109.88
Cost of 1 metre ₹110.99
Say ₹111.00