Rate analysis
Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete
DSR rate₹22,578.75as per item analysis
1800 mm dia RCC pipes. (Laying by manual/ machanical means)
- Item code
- 19.36.6
- Sub-head
- SH 19 · DRAINAGE
- Unit
- See analysis
- Source row
- 3749
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail for 10 metre | |||||
| MATERIALS : | |||||
| 1739 | RCC pipe 1800 mm dia pipe NP-4 spigot | metre | 10 | ₹14,605.00 | ₹1,46,050.00 |
| 2336 | RCC pipe above 1200 mm dia and upto | — | — | — | — |
| — | 1800 mm dia | 100 metre | 0.1 | ₹0.00 | ₹0.00 |
| 0367 | Portland Cement (OPC-43 grade) | tonne | 0.049 | ₹5,156.00 | ₹252.64 |
| 2209 | Carriage of Cement | tonne | 0.049 | ₹0.00 | ₹0.00 |
| 0983 | Fine sand (zone IV) | cum | 0.055 | ₹980.00 | ₹53.90 |
| 2261 | Carriage of Fine sand (1 part badarpur sand : 2 parts jamuna sand) | cum | 0.055 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 1.15 | ₹897.00 | ₹1,031.55 |
| 0124 | Mason 2nd class | day | 1.15 | ₹816.00 | ₹938.40 |
| 0114 | Beldar | day | 13 | ₹736.00 | ₹9,568.00 |
| 0101 | Bhisti | day | 1 | ₹816.00 | ₹816.00 |
| — | Detail of cost for 10 metre | — | — | — | ₹2,25,787.34 |
| — | Rate per metre | — | — | — | ₹22,578.73 |
Rate build-up
| TOTAL | ₹1,58,710.49 |
| Add 1 % Water charges on "W" | ₹1,587.10 |
| TOTAL | ₹1,60,297.59 |
| Add GST on "X" (multiplying factor 0.2127) | ₹34,095.30 |
| TOTAL | ₹1,94,392.89 |
| Add 15% CPOH on "Y" | ₹29,158.93 |
| TOTAL | ₹2,23,551.82 |
| Add Cess @ 1% on "Z" | ₹2,235.52 |
| Say | ₹22,578.75 |