DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.36.3 rate analysis

Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 900 mm dia RCC pipes.

Published rate₹7,397.40DSR 2023
Rate analysis

Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

DSR rate₹7,397.40as per item analysis

900 mm dia RCC pipes.

Item code
19.36.3
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
3749

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail for 10 metre
MATERIALS :
1736 RCC pipe 900 mm dia pipe NP-4 spigot metre 10 ₹4,815.00 ₹48,150.00
2331 R.C.C. pipes 900 mm dia 100 metre 0.1 ₹0.00 ₹0.00
0367 Portland Cement (OPC-43 grade) tonne 0.025 ₹5,156.00 ₹128.90
2209 Carriage of Cement tonne 0.025 ₹0.00 ₹0.00
0983 Fine sand (zone IV) cum 0.033 ₹980.00 ₹32.34
2261 Carriage of Fine sand (1 part badarpur sand : 2 parts jamuna sand) cum 0.033 ₹0.00 ₹0.00
LABOUR
0123 Mason 1st class day 0.625 ₹897.00 ₹560.63
0124 Mason 2nd class day 0.625 ₹816.00 ₹510.00
0114 Beldar day 3 ₹736.00 ₹2,208.00
0101 Bhisti day 0.5 ₹816.00 ₹408.00
Detail of cost for 10 metre ₹73,974.08
Rate per metre ₹7,397.41

Rate build-up

TOTAL ₹51,997.87
Add 1 % Water charges on "W" ₹519.98
TOTAL ₹52,517.85
Add GST on "X" (multiplying factor 0.2127) ₹11,170.55
TOTAL ₹63,688.40
Add 15% CPOH on "Y" ₹9,553.26
TOTAL ₹73,241.66
Add Cess @ 1% on "Z" ₹732.42
Say ₹7,397.40