DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.36.1 rate analysis

Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 450 mm dia RCC pipes.

Published rate₹3,053.55DSR 2023
Rate analysis

Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

DSR rate₹3,053.55as per item analysis

450 mm dia RCC pipes.

Item code
19.36.1
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
3749

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail for 10 metre
MATERIALS :
1734 RCC pipe 450 mm dia NP-4 spigot metre 10 ₹1,870.00 ₹18,700.00
2299 Carriage of R.C.C. pipes 450 & 500 mm dia 100 metre 0.1 ₹0.00 ₹0.00
0367 Portland Cement (OPC-43 grade) tonne 0.012 ₹5,156.00 ₹61.87
2209 Carriage of Cement tonne 0.012 ₹0.00 ₹0.00
0983 Fine sand (zone IV) cum 0.017 ₹980.00 ₹16.66
2261 Carriage of Fine sand (1 part badarpur sand : 2 parts jamuna sand) cum 0.017 ₹0.00 ₹0.00
LABOUR
0123 Mason 1st class day 0.375 ₹897.00 ₹336.38
0124 Mason 2nd class day 0.375 ₹816.00 ₹306.00
0114 Beldar day 2.41 ₹736.00 ₹1,773.76
0101 Bhisti day 0.33 ₹816.00 ₹269.28
Detail of cost for 10 metre ₹30,535.40
Rate per metre ₹3,053.54

Rate build-up

TOTAL ₹21,463.95
Add 1 % Water charges on "W" ₹214.64
TOTAL ₹21,678.59
Add GST on "X" (multiplying factor 0.2127) ₹4,611.04
TOTAL ₹26,289.63
Add 15% CPOH on "Y" ₹3,943.44
TOTAL ₹30,233.07
Add Cess @ 1% on "Z" ₹302.33
Say ₹3,053.55

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook