DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.34.2 rate analysis

Providing and fixing S.W. intercepting trap in manholes with stiff mixture of cement mortar 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 150 mm dia

Published rate₹602.65DSR 2023
Rate analysis

Providing and fixing S.W. intercepting trap in manholes with stiff mixture of cement mortar 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete :

DSR rate₹602.65as per item analysis

150 mm dia

Item code
19.34.2
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
3527

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost of 10 nos.
MATERIAL
7129 S.W. intercepting trap 150 mm dia each 10 ₹262.00 ₹2,620.00
9977 Carriage of trap L.S. 20.8 ₹2.27 ₹47.22
0367 Portland Cement (OPC-43 grade) tonne 0.019 ₹5,156.00 ₹97.96
2209 Carriage of Cement tonne 0.019 ₹0.00 ₹0.00
0983 Fine sand (zone IV) cum 0.014 ₹980.00 ₹13.72
2261 Carriage of Fine sand (1 part badarpur sand : 2 parts jamuna sand) cum 0.014 ₹0.00 ₹0.00
1881 Spun yarn kilogram 1.8 ₹61.00 ₹109.80
LABOUR
0123 Mason 1st class day 0.3 ₹897.00 ₹269.10
0124 Mason 2nd class day 0.3 ₹816.00 ₹244.80
0114 Beldar day 0.8 ₹736.00 ₹588.80
0101 Bhisti day 0.3 ₹816.00 ₹244.80

Rate build-up

TOTAL ₹4,236.20
Add 1 % Water charges on "W" ₹42.36
TOTAL ₹4,278.56
Add GST on "X" (multiplying factor 0.2127) ₹910.05
TOTAL ₹5,188.61
Add 15% CPOH on "Y" ₹778.29
TOTAL ₹5,966.90
Add Cess @ 1% on "Z" ₹59.67
Cost of 10 nos. ₹6,026.57
Cost of one no. ₹602.66
Say ₹602.65