Rate analysis
Inside dimensions 455x610 mm and 45 cm deep for single pipe line :
DSR rate₹6,937.90as per item analysis
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
- Item code
- 19.30.1.1
- Sub-head
- SH 19 · DRAINAGE
- Unit
- See analysis
- Source row
- 3260
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one chamber | |||||
| Cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) | |||||
| 1.22mx1.065mx0.15 m= 0.195 cum Say 0.20 cum | |||||
| 4.1.11 | Rate as per item no 4.1.11 of SH : Concrete Work | cum | 0.2 | ₹6,189.65 | ₹1,237.93 |
| Brick work in bricks of clas designation 7.5 in cement mortar 1:4 ( 1 cement : 4 coarse sand) | |||||
| 3.05 m x 0.23m x0.30 m = 0.210 cum | |||||
| Less pipe | |||||
| 2x3.14/4x(0.10)²x0.23 m = (-) 0.004 cum | |||||
| Net Qty= 0.206 cum Say 0.21 cum | |||||
| 6.1.1 | Rate as per item no 6.1.1 of SH : Brick Work | cum | 0.21 | ₹7,370.65 | ₹1,547.84 |
| 12 mm cement plaster 1:3 ( 1 cement : 3 coarse sand) finished with floating coat of neat cement | |||||
| Wall : 2.13x0.30 m = 0.639 sqm | |||||
| Bed : 0.61x0.455 m = 0.278 sqm | |||||
| Total= 0.917 sqm | |||||
| Less pipe 2x3.14/4x(0.10)² = (-) 0.016 sqm | |||||
| Net Qty= 0.901 sqm Say 0.90 sqm | |||||
| 13.9.1 | Rate as per item no 13.9.1 of SH : Finishing | sqm | 0.9 | ₹449.55 | ₹404.60 |
| Cement concrete 1:1.5:3 ( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) | |||||
| 3.05x0.23x0.15 = 0.105 cum say 0.11 cum | |||||
| 5.1.2 | Rate as per item no. 5.1.2 of SH : RCC work | cum | 0.11 | ₹9,045.75 | ₹995.03 |
| Form work | |||||
| Outer periphery 3.73x0.15 m = 0.56 sqm | |||||
| 5.9.2 | Rate as per item no 5.9.2 of SH : RCC | sqm | 0.56 | ₹842.50 | ₹471.80 |
| 1354 | Rectangular cover 455x610 mm with frame (low duty) | each | 1 | ₹1,540.00 | ₹1,540.00 |
| 9977 | Carriage of C.I.cover and frame | L.S. | 7.15 | ₹2.27 | ₹16.23 |
| 9999 | Painting of C.I. Cover and frame with coal tar | L.S. | 7.15 | ₹2.27 | ₹16.23 |
| 9999 | Sundries | L.S. | 13.52 | ₹2.27 | ₹30.69 |
Rate build-up
| TOTAL | ₹6,260.35 |
| Add 1 % Water charges on "W-A" | ₹16.03 |
| TOTAL | ₹6,276.38 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹344.40 |
| TOTAL | ₹6,620.78 |
| Add 15% CPOH on "Y-A" | ₹294.54 |
| TOTAL | ₹6,915.32 |
| Add Cess @ 1% on "Z-A" | ₹22.58 |
| Cost of one chamber | ₹6,937.90 |
| Say | ₹6,937.90 |