Rate analysis
Extra for depth of manholes dismantled :
DSR rate₹2,045.50as per item analysis
Rectangular manhole 90x80 cm and beyond 45 cm depth
- Item code
- 19.25.1
- Sub-head
- SH 19 · DRAINAGE
- Unit
- See analysis
- Source row
- 2853
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one metre | |||||
| Dismantling of second class brick work in cement mortar 1:5 (1 Cement : 5 fine sand) | |||||
| 4.32x0.23x1.0m = 0.994 cum Say 0.99 cum | |||||
| 15.7.4 | Rate as per item no. 15.7.4 of SH :dismantling and dimolishing | cum | 0.99 | ₹2,060.20 | ₹2,039.60 |
| 9999 | Removing of M.S. foot rests | L.S. | 1.82 | ₹2.27 | ₹4.13 |
Rate build-up
| TOTAL | ₹2,043.73 |
| Add 1 % Water charges on "W-A" | ₹0.04 |
| TOTAL | ₹2,043.77 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹0.89 |
| TOTAL | ₹2,044.66 |
| Add 15% CPOH on "Y-A" | ₹0.76 |
| TOTAL | ₹2,045.42 |
| Add Cess @ 1% on "Z-A" | ₹0.06 |
| Cost for one metre | ₹2,045.48 |
| Say | ₹2,045.50 |