DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.21.1 rate analysis

Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete : For pipes 100 to 250 mm diameter

Published rate₹810.45DSR 2023
Rate analysis

Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete :

DSR rate₹810.45as per item analysis

For pipes 100 to 250 mm diameter

Item code
19.21.1
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
2423

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one connection
MATERIAL
cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
= 0.30x0.30x0.23 m = 0.0207 cum
Less pipe = 1/2x3.14x0.23x0.23x0.23 = 0.0096 cum
= 0.0111 cum Say 0.01 cum
4.1.3 Rate as per item no. 4.1.3 of SH : Concrete cum 0.01 ₹7,878.50 ₹78.79
12 mm cement plater 1:3 ( 1 cement : 3 coarse sand ) finished with a floating coat of neat cement
2x0.35x0.35 =0.25sqm
13.9.1 Rate as per item no 13.9.1 of SH : Finishing sqm 0.25 ₹449.55 ₹112.39
LABOUR
(For cutting holes average size 30x30 cm in 23 cm thick wall and making channel etc.)
0123 Mason 1st class day 0.12 ₹897.00 ₹107.64
0124 Mason 2nd class day 0.12 ₹816.00 ₹97.92
0114 Beldar day 0.25 ₹736.00 ₹184.00
9999 Add for delay sundries etc. L.S. 20.15 ₹2.27 ₹45.74

Rate build-up

TOTAL ₹626.48
Add 1 % Water charges on "W-A" ₹4.35
TOTAL ₹630.83
Add GST on "X-A" (multiplying factor 0.2127) ₹93.51
TOTAL ₹724.34
Add 15% CPOH on "Y-A" ₹79.97
TOTAL ₹804.31
Add Cess @ 1% on "Z-A" ₹6.13
Cost for 1 connection ₹810.44
Say ₹810.45

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.