Rate analysis
Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality M D - 10
DSR rate₹1,172.60as per item analysis
Circular shape 500 mm internal diameter
- Item code
- 19.19.2.2
- Sub-head
- SH 19 · DRAINAGE
- Unit
- See analysis
- Source row
- 2232
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one no. | |||||
| MATERIAL | |||||
| 7134 | Circular shape 500 mm dia precast R.C.C. manhole cover with frame - M.D. - 10 | each | 1 | ₹605.00 | ₹605.00 |
| 9977 | Carriage of manhole cover | L.S. | 6.76 | ₹2.27 | ₹15.35 |
| Cement concrete 1:2:4 ( 1 cement : 2 coarse sand : 4 grade stone aggregate 20 mm nominal size ) | |||||
| 3.14/4x(0.95)²x0.15 = 0.1064 cum | |||||
| Less cover with frame | |||||
| 3.14/4x(0.8)²x0.15 = (-) 0.0754 cum | |||||
| = 0.031 cum Say 0.03 cum | |||||
| 4.1.3 | Rate as per item no. 4.1.3 of SH : Concrete Work | cum | 0.03 | ₹7,878.50 | ₹236.36 |
| 9999 | Sundries | L.S. | 16.64 | ₹2.27 | ₹37.77 |
Rate build-up
| TOTAL | ₹894.48 |
| Add 1 % Water charges on "W-A" | ₹6.58 |
| TOTAL | ₹901.06 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹141.38 |
| TOTAL | ₹1,042.44 |
| Add 15% CPOH on "Y-A" | ₹120.91 |
| TOTAL | ₹1,163.35 |
| Add Cess @ 1% on "Z-A" | ₹9.27 |
| Cost for 1 no. | ₹1,172.62 |
| Say | ₹1,172.60 |