Rate analysis
Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality L D- 2.5
DSR rate₹1,169.65as per item analysis
Circular shape 450 mm internal diameter
- Item code
- 19.19.1.3
- Sub-head
- SH 19 · DRAINAGE
- Unit
- See analysis
- Source row
- 2232
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one no. | |||||
| MATERIAL | |||||
| 7132 | Circular shape 450 mm dia precast R.C.C. manhole cover with frame - L.D. - 2.5 | each | 1 | ₹610.00 | ₹610.00 |
| 9977 | Carriage of manhole cover | L.S. | 6.76 | ₹2.27 | ₹15.35 |
| Cement concrete 1:2:4 ( 1 cement : 2 coarse sand : 4 grade stone aggregate 20 mm nominal size ) | |||||
| 3.14/4x(0.775)²x0.15 = 0.0708 cum | |||||
| Less cover with frame | |||||
| 3.14/4x(0.625)²x0.15 = (-) 0.0460 cum | |||||
| = 0.0248 cum Say 0.03 cum | |||||
| 4.1.3 | Rate as per item no. 4.1.3 of SH : Concrete Work | cum | 0.03 | ₹7,878.50 | ₹236.36 |
| 9999 | Sundries | L.S. | 13.52 | ₹2.27 | ₹30.69 |
Rate build-up
| TOTAL | ₹892.40 |
| Add 1 % Water charges on "W-A" | ₹6.56 |
| TOTAL | ₹898.96 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹140.94 |
| TOTAL | ₹1,039.90 |
| Add 15% CPOH on "Y-A" | ₹120.53 |
| TOTAL | ₹1,160.43 |
| Add Cess @ 1% on "Z-A" | ₹9.24 |
| Cost for 1 no. | ₹1,169.67 |
| Say | ₹1,169.65 |