DSR 2023 · SH 19 · DRAINAGE

CPWD DSR item 19.18.2 rate analysis

Supplying and fixing C.I. cover without frame for manholes : 500 mm diameter C.I. cover (medium duty) the weight of the cover to be not less than 58 kg

Published rate₹3,441.20DSR 2023
Rate analysis

Supplying and fixing C.I. cover without frame for manholes :

DSR rate₹3,441.20as per item analysis

500 mm diameter C.I. cover (medium duty) the weight of the cover to be not less than 58 kg

Item code
19.18.2
Sub-head
SH 19 · DRAINAGE
Unit
See analysis
Source row
2173

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one cover
MATERIAL
1357 500 mm dia cover without frame (medium duty) each 1 ₹2,300.00 ₹2,300.00
9977 Carriage of C.I. cover L.S. 13.47 ₹2.27 ₹30.58
LABOUR
0114 Beldar day 0.12 ₹736.00 ₹88.32

Rate build-up

TOTAL ₹2,418.90
Add 1 % Water charges on "W" ₹24.19
TOTAL ₹2,443.09
Add GST on "X" (multiplying factor 0.2127) ₹519.65
TOTAL ₹2,962.74
Add 15% CPOH on "Y" ₹444.41
TOTAL ₹3,407.15
Add Cess @ 1% on "Z" ₹34.07
Cost for 1 no. ₹3,441.22
Say ₹3,441.20