DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.82.8 rate analysis

Dismantling old C.I. pipes including excavation and refilling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, including stacking of pipes at site lead up to 50 metre: 350 mm diameter C.I. pipe

Published rate₹538.00DSR 2023
Rate analysis

Dismantling old C.I. pipes including excavation and refilling trenches after taking out the pipes, breaking lead caulked joints, melting of lead and making into blocks, including stacking of pipes at site lead up to 50 metre:

DSR rate₹538.00as per item analysis

350 mm diameter C.I. pipe

Item code
18.82.8
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
8655

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 40.26 m or 11 nos. joints.
Earth work in excavation for dismantling pipes including refilling of excavated earth
1x40.26x.75x0.75 m=22.65 cum
Deduct for pipe 1x40.26x3.14/4x(0.378)² =(-) 4.51 cum
Total= 18.14 cum
2.8.1 (Rate as per item no. 2.8.1 of SH: Earth work) cum 18.14 ₹260.30 ₹4,721.84
2.25 (Rate as per item No.2.25 of SH Earth work) cum 18.14 ₹196.00 ₹3,555.44
Breaking lead caulked joints, blocks and stacking
MATERIAL
0761 Fuel wood quintal 1.213 ₹550.00 ₹667.15
0771 Kerosene oil litre 1.515 ₹50.00 ₹75.75
LABOUR
0117 Assistant Fitter or 2nd class Fitter day 1.75 ₹816.00 ₹1,428.00
0114 Beldar day 9.5 ₹736.00 ₹6,992.00
9988 Sundries and carriage L.S. 107.64 ₹2.27 ₹244.34

Rate build-up

TOTAL ₹17,684.52
Add 1 % Water charges on "W-A" ₹94.07
TOTAL ₹17,778.59
Add GST on "X-A" (multiplying factor 0.2127) ₹2,020.93
TOTAL ₹19,799.52
Add 15% CPOH on "Y-A" ₹1,728.34
TOTAL ₹21,527.86
Add Cess @ 1% on "Z-A" ₹132.51
Cost of 40.26 metre ₹21,660.37
Cost of one metre ₹538.01
Say ₹538.00