DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.81.9 rate analysis

Extra for every operation of disinfecting the C.I. main by flushing with water containing bleaching powder @ 0.5 gms per litre of water and cleaning the same with fresh water, including getting the samples of water tested in the municipal laboratory : 400 mm diameter C.I. pipe

Published rate₹3,011.20DSR 2023
Rate analysis

Extra for every operation of disinfecting the C.I. main by flushing with water containing bleaching powder @ 0.5 gms per litre of water and cleaning the same with fresh water, including getting the samples of water tested in the municipal laboratory :

DSR rate₹3,011.20as per item analysis

400 mm diameter C.I. pipe

Item code
18.81.9
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
8414

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 metres
MATERIAL
1301 Bleaching powder quintal 0.063 ₹1,700.00 ₹107.10
LABOUR
0116 Fitter (grade 1) day 0.8 ₹897.00 ₹717.60
0114 Beldar day 1.7 ₹736.00 ₹1,251.20
9999 Sundries including testing of samples L.S. 17.94 ₹2.27 ₹40.72

Rate build-up

TOTAL ₹2,116.62
Add 1 % Water charges on "W" ₹21.17
TOTAL ₹2,137.79
Add GST on "X" (multiplying factor 0.2127) ₹454.71
TOTAL ₹2,592.50
Add 15% CPOH on "Y" ₹388.88
TOTAL ₹2,981.38
Add Cess @ 1% on "Z" ₹29.81
Cost of 100 metre ₹3,011.19
Say ₹3,011.20