DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.81.5 rate analysis

Extra for every operation of disinfecting the C.I. main by flushing with water containing bleaching powder @ 0.5 gms per litre of water and cleaning the same with fresh water, including getting the samples of water tested in the municipal laboratory : 200 mm diameter C.I. pipe

Published rate₹1,753.10DSR 2023
Rate analysis

Extra for every operation of disinfecting the C.I. main by flushing with water containing bleaching powder @ 0.5 gms per litre of water and cleaning the same with fresh water, including getting the samples of water tested in the municipal laboratory :

DSR rate₹1,753.10as per item analysis

200 mm diameter C.I. pipe

Item code
18.81.5
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
8414

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 metres
MATERIAL
1301 Bleaching powder quintal 0.016 ₹1,700.00 ₹27.20
LABOUR
0116 Fitter (grade 1) day 0.58 ₹897.00 ₹520.26
0114 Beldar day 0.9 ₹736.00 ₹662.40
9999 Sundries including testing of samples L.S. 9.88 ₹2.27 ₹22.43

Rate build-up

TOTAL ₹1,232.29
Add 1 % Water charges on "W" ₹12.32
TOTAL ₹1,244.61
Add GST on "X" (multiplying factor 0.2127) ₹264.73
TOTAL ₹1,509.34
Add 15% CPOH on "Y" ₹226.40
TOTAL ₹1,735.74
Add Cess @ 1% on "Z" ₹17.36
Cost of 100 metre ₹1,753.10
Say ₹1,753.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook