DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.68.2 rate analysis

Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523 : Above 600 mm dia

Published rate₹26,696.10per quintal
Rate analysis

Providing and laying D.I. specials of class K-12 suitable for push-on jointing as per IS : 9523 :

DSR rate₹26,696.10per quintal

Above 600 mm dia

Item code
18.68.2
Sub-head
SH 18 · WATER SUPPLY
Unit
quintal
Source row
6005

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 quintal
MATERIAL
7683 Ductile Iron K - 12 specials suitable for push on jointing over 600mm dia quintal 1 ₹18,300.00 ₹18,300.00
2309 Carriage of Cast iron fittings tonne 0.1 ₹0.00 ₹0.00
Labour for laying
18.24 Rate as per Item Number 18.24 of SH: Water Supply quintal 1 ₹661.85 ₹661.85

Rate build-up

TOTAL ₹18,961.85
Add 1 % Water charges on "W-A" ₹183.00
TOTAL ₹19,144.85
Add GST on "X-A" (multiplying factor 0.2127) ₹3,931.33
TOTAL ₹23,076.18
Add 15% CPOH on "Y-A" ₹3,362.15
TOTAL ₹26,438.33
Add Cess @ 1% on "Z-A" ₹257.76
Cost of 1 quintal ₹26,696.09
Say ₹26,696.10

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook