DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.47.4 rate analysis

Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required : 32 mm nominal bore

Published rate₹1,000.15DSR 2023
Rate analysis

Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required :

DSR rate₹1,000.15as per item analysis

32 mm nominal bore

Item code
18.47.4
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
5010

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one no.
MATERIAL
1644 G.I. Union 32 mm nominal bore each 1 ₹160.00 ₹160.00
9988 Carriage of materials and sundries L.S. 1.82 ₹2.27 ₹4.13
LABOUR
0116 Fitter (grade 1) day 0.33 ₹897.00 ₹296.01
0114 Beldar day 0.33 ₹736.00 ₹242.88

Rate build-up

TOTAL ₹703.02
Add 1 % Water charges on "W" ₹7.03
TOTAL ₹710.05
Add GST on "X" (multiplying factor 0.2127) ₹151.03
TOTAL ₹861.08
Add 15% CPOH on "Y" ₹129.16
TOTAL ₹990.24
Add Cess @ 1% on "Z" ₹9.90
Cost for one no. ₹1,000.14
Say ₹1,000.15