Rate analysis
Providing and fixing G.I. Union in existing G.I. pipe line, cutting and threading the pipe and making long screws, including excavation, refilling the earth or cutting of wall and making good the same complete wherever required :
DSR rate₹857.85as per item analysis
20 mm nominal bore
- Item code
- 18.47.2
- Sub-head
- SH 18 · WATER SUPPLY
- Unit
- See analysis
- Source row
- 5010
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one no. | |||||
| MATERIAL | |||||
| 1642 | G.I. Union 20 mm nominal bore | each | 1 | ₹60.00 | ₹60.00 |
| 9988 | Carriage of materials and sundries | L.S. | 1.82 | ₹2.27 | ₹4.13 |
| LABOUR | |||||
| 0116 | Fitter (grade 1) | day | 0.33 | ₹897.00 | ₹296.01 |
| 0114 | Beldar | day | 0.33 | ₹736.00 | ₹242.88 |
Rate build-up
| TOTAL | ₹603.02 |
| Add 1 % Water charges on "W" | ₹6.03 |
| TOTAL | ₹609.05 |
| Add GST on "X" (multiplying factor 0.2127) | ₹129.54 |
| TOTAL | ₹738.59 |
| Add 15% CPOH on "Y" | ₹110.79 |
| TOTAL | ₹849.38 |
| Add Cess @ 1% on "Z" | ₹8.49 |
| Cost for one no. | ₹857.87 |
| Say | ₹857.85 |