Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work : Sub analysis item for sand filling component

Published rate₹2,087.30DSR 2023
Rate analysis

Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work :

DSR rate₹2,087.30as per item analysis

Sub analysis item for sand filling component

Item code
18.41.1A
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
4513

Cost components

CodeDescriptionUnitQuantityRateAmount
Sub analysis item for sand filling component
MATERIAL
6501 Sand zone V (Jamuna) cum 1 ₹1,320.00 ₹1,320.00
2335 Carriage of Jamuna sand cum 1 ₹0.00 ₹0.00
Labour:
0114 Beldar day 0.09 ₹736.00 ₹66.24
0115 Coolie day 0.11 ₹736.00 ₹80.96

Rate build-up

TOTAL ₹1,467.20
Add 1 % Water charges on "W" ₹14.67
TOTAL ₹1,481.87
Add GST on "X" (multiplying factor 0.2127) ₹315.19
TOTAL ₹1,797.06
Add 15% CPOH on "Y" ₹269.56
TOTAL ₹2,066.62
Add Cess @ 1% on "Z" ₹20.67
Cost of one cum. ₹2,087.29
Say ₹2,087.30