Rate analysis
Providing and filling sand of grading zone V or coarser grade, allround the G.I. pipes in external work :
DSR rate₹2,087.30as per item analysis
Sub analysis item for sand filling component
- Item code
- 18.41.1A
- Sub-head
- SH 18 · WATER SUPPLY
- Unit
- See analysis
- Source row
- 4513
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Sub analysis item for sand filling component | |||||
| MATERIAL | |||||
| 6501 | Sand zone V (Jamuna) | cum | 1 | ₹1,320.00 | ₹1,320.00 |
| 2335 | Carriage of Jamuna sand | cum | 1 | ₹0.00 | ₹0.00 |
| Labour: | |||||
| 0114 | Beldar | day | 0.09 | ₹736.00 | ₹66.24 |
| 0115 | Coolie | day | 0.11 | ₹736.00 | ₹80.96 |
Rate build-up
| TOTAL | ₹1,467.20 |
| Add 1 % Water charges on "W" | ₹14.67 |
| TOTAL | ₹1,481.87 |
| Add GST on "X" (multiplying factor 0.2127) | ₹315.19 |
| TOTAL | ₹1,797.06 |
| Add 15% CPOH on "Y" | ₹269.56 |
| TOTAL | ₹2,066.62 |
| Add Cess @ 1% on "Z" | ₹20.67 |
| Cost of one cum. | ₹2,087.29 |
| Say | ₹2,087.30 |