DSR 2023 · SH 18 · WATER SUPPLY

CPWD DSR item 18.23 rate analysis

Laying in position centrifugally cast (spun) iron S&S or flanged pipes (excluding cost of pipe).

Published rate₹361.65DSR 2023
Rate analysis

Laying in position centrifugally cast (spun) iron S&S or flanged pipes (excluding cost of pipe).

DSR rate₹361.65as per item analysis
Item code
18.23
Sub-head
SH 18 · WATER SUPPLY
Unit
See analysis
Source row
2574

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 5.14 quintal
10 m of 200 mm dia C.I. pipe class 'A'
Weight = (2x257) = 514kg = 5.14 quintal
LABOUR for laying pipe
0116 Fitter (grade 1) day 0.17 ₹897.00 ₹152.49
0117 Assistant Fitter or 2nd class Fitter day 0.17 ₹816.00 ₹138.72
0114 Beldar day 1.33 ₹736.00 ₹978.88
9999 Sundries L.S. 16.12 ₹2.27 ₹36.59

Rate build-up

TOTAL ₹1,306.68
Add 1 % Water charges on "W" ₹13.07
TOTAL ₹1,319.75
Add GST on "X" (multiplying factor 0.2127) ₹280.71
TOTAL ₹1,600.46
Add 15% CPOH on "Y" ₹240.07
TOTAL ₹1,840.53
Add Cess @ 1% on "Z" ₹18.41
Cost of 5.14 quintal ₹1,858.94
Cost of one quintal ₹361.66
Say ₹361.65