Rate analysis
Laying in position centrifugally cast (spun) iron S&S or flanged pipes (excluding cost of pipe).
DSR rate₹361.65as per item analysis
- Item code
- 18.23
- Sub-head
- SH 18 · WATER SUPPLY
- Unit
- See analysis
- Source row
- 2574
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 5.14 quintal | |||||
| 10 m of 200 mm dia C.I. pipe class 'A' | |||||
| Weight = (2x257) = 514kg = 5.14 quintal | |||||
| LABOUR for laying pipe | |||||
| 0116 | Fitter (grade 1) | day | 0.17 | ₹897.00 | ₹152.49 |
| 0117 | Assistant Fitter or 2nd class Fitter | day | 0.17 | ₹816.00 | ₹138.72 |
| 0114 | Beldar | day | 1.33 | ₹736.00 | ₹978.88 |
| 9999 | Sundries | L.S. | 16.12 | ₹2.27 | ₹36.59 |
Rate build-up
| TOTAL | ₹1,306.68 |
| Add 1 % Water charges on "W" | ₹13.07 |
| TOTAL | ₹1,319.75 |
| Add GST on "X" (multiplying factor 0.2127) | ₹280.71 |
| TOTAL | ₹1,600.46 |
| Add 15% CPOH on "Y" | ₹240.07 |
| TOTAL | ₹1,840.53 |
| Add Cess @ 1% on "Z" | ₹18.41 |
| Cost of 5.14 quintal | ₹1,858.94 |
| Cost of one quintal | ₹361.66 |
| Say | ₹361.65 |