DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.66.2 rate analysis

Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes and fittings with one coat of synthetic enamel paint of any colour such as chocolate, grey or buff etc : 75 mm diameter pipe

Published rate₹29.55per metre
Rate analysis

Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes and fittings with one coat of synthetic enamel paint of any colour such as chocolate, grey or buff etc :

DSR rate₹29.55per metre

75 mm diameter pipe

Item code
17.66.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
metre
Source row
4267

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metres
Painting one coat with paint of any colour such as chocolate,grey or buff etc.
13.99.1 (Rate as per item no 13.99.1 of S.H. Finishing) sqm 2.577 ₹102.80 ₹264.92
9999 Add for delay L.S. 9.49 ₹2.27 ₹21.54

Rate build-up

TOTAL ₹286.46
Add 1 % Water charges on "W-A" ₹0.22
TOTAL ₹286.68
Add GST on "X-A" (multiplying factor 0.2127) ₹4.63
TOTAL ₹291.31
Add 15% CPOH on "Y-A" ₹3.96
TOTAL ₹295.27
Add Cess @ 1% on "Z-A" ₹0.30
Cost of 10 metres ₹295.57
Cost of 1 metre ₹29.56
Say ₹29.55

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook